Network Refresh Planning: When to Replace Switches, Firewalls and Wi-Fi, and How to Cut Over Without Downtime

Most office networks are replaced in a rush after something fails or a support date passes. Here is how to tell when a refresh is due, what each device type typically lasts, the design decisions that matter in 2026, and a cutover plan that keeps the office working.

network refresh

The short answer

  • Plan the refresh around support dates, not failures. A switch or firewall without security updates is a risk long before it stops working.
  • Firewalls and Wi-Fi age fastest. Expect roughly five to seven years from them, seven to ten from switches, and fifteen or more from good cabling.
  • The big 2026 decisions are cloud-managed or locally managed, licence or no licence, and whether new Wi-Fi needs faster switch ports and more power.
  • Cut over in one prepared weekend. Everything configured and labelled before it arrives on site, with the old gear left in place until Monday morning proves the new network works.

Signs a refresh is due

  • A support date is coming. Cisco Catalyst 2960-X switches, still common in GTA offices, stopped getting software fixes in October 2023 and lose all support on October 31, 2027. Meraki MX84 security appliances reached end of support on October 31, 2026. Older SonicWall Gen 6 firewalls passed their end-of-support dates in 2026.
  • Wi-Fi complaints have become routine. Dead spots, video calls dropping in meeting rooms, and slowdowns when everyone arrives in the morning.
  • The network cannot be segmented. Guests, cameras, phones and staff computers all share one flat network because the equipment cannot do better.
  • Nobody can see what is happening. No central dashboard, no alerts, and troubleshooting means walking to the comms room.
  • Your internet got faster but the office did not. A gigabit or multi-gigabit connection held back by an old firewall that cannot inspect traffic at that speed.
  • An insurer or client asked. Questionnaires now ask directly about unsupported network equipment.

How long network equipment lasts

These are practical service lives for small and mid-sized offices, not the point at which equipment physically fails. The deciding factor is usually the vendor’s security support date.

UPS batteries3 to 5 years
Firewall5 to 7 years
Wi-Fi access points5 to 7 years
Switches7 to 10 years
Category 6 cabling15 years or more

Typical service lives in office environments. Check each model’s end-of-support date, which can come sooner.

Design decisions that matter in 2026

Decision Option A Option B What usually decides it
Management Cloud-managed, such as Cisco Meraki or Aruba Self-hosted or local controller, such as UniFi How many sites, and who manages the network day to day
Cost model Annual licence per device, support included No licence; buy the hardware outright Whether you prefer predictable subscriptions or lower ongoing cost
Wi-Fi generation Wi-Fi 6E, mature and well priced Wi-Fi 7, faster with newer laptops How long you plan to keep the access points
Switch ports for access points 1 Gbps 2.5 Gbps multi-gig Wi-Fi 6E and 7 access points can exceed 1 Gbps under load
Power over Ethernet Standard PoE+ budget Larger budget or 802.3bt ports Newer access points, cameras and video bars draw more power
Firewall sizing Sized for today’s internet speed Sized for inspected throughput at your next upgrade Security features cut real throughput well below the headline number

In Canada, the 6 GHz band that Wi-Fi 6E and Wi-Fi 7 use has been open for indoor low-power use since 2021, so offices can take full advantage of it. Newer access points perform best with multi-gig switch ports and enough power budget, which is why Wi-Fi and switches are best planned together. Our business Wi-Fi installation page covers the wireless side in more depth.

A realistic refresh timeline

A typical ten-week network refresh timelineWeeks one and two: audit the current network, devices and cabling. Weeks two to four: design the new network, including segments, Wi-Fi coverage and firewall sizing. Weeks four to seven: order equipment, allowing for supplier lead times. Weeks six to eight: configure and label everything in advance on a test bench. Week eight: cut over during a weekend with the old equipment still in place. Weeks nine and ten: tune Wi-Fi, fix small issues and finish documentation.12345678910WeekAuditDesignOrderPre-configureCutoverTune and documentsupplier lead timesweekend
Lead times on switches and access points vary by brand and season. Ordering early is the simplest way to keep the cutover date.

The refresh, step by step

  1. Audit what you have. Every switch, firewall, access point and UPS with model, age, support date and what plugs into it. Test the cabling at the same time; a refresh on top of faulty cable runs fixes nothing.
  2. List what the network must do. Number of people and devices, phones, cameras, guest access, remote workers, any equipment that needs its own segment, and the internet speed you expect in three years.
  3. Design the segments first. Staff, servers, phones, guests, cameras and printers, building systems. Decide what may talk to what before choosing hardware. Our VLAN guide explains the idea.
  4. Plan Wi-Fi from the floor plan. Place access points for coverage and capacity, then confirm with a site survey once installed.
  5. Choose the platform and size it. Management model, licensing, PoE budget, multi-gig ports and firewall throughput with security features on.
  6. Order early. Include spares for anything critical, such as a spare switch or power supply.
  7. Configure everything before it reaches site. Pre-load configurations, label every device and cable, and test on a bench.
  8. Cut over on a weekend. Move connections device by device, test phones, printers, cameras, card readers and line-of-business apps, and keep the old equipment powered off but in place until Monday.
  9. Tune and document. Adjust Wi-Fi after a week of real use, then record the final design, passwords in a password manager, and support dates for the next refresh.

Do not forget the things that are not computers

Door access controllers, alarm panels, elevator phones, payment terminals and building management systems often sit on the office network with fixed addresses nobody wrote down. Find them during the audit, or the first sign of a problem will be a locked door on Monday morning.

Budgeting the refresh

For a typical 20 to 50 person office, the main costs are the firewall, the switches, the access points and labour for design, configuration and cutover. Cloud-managed platforms add an annual licence per device, which includes support and updates; licence-free platforms cost less over time but rely more on whoever manages them. Spreading the refresh is possible, firewall first if it is the oldest or least supported piece, but switches and Wi-Fi are best done together because of the power and port-speed links between them.

We plan and carry out network refreshes for offices across Toronto and the GTA through our network and firewall support, with platform-specific work on Cisco Meraki and UniFi. Moving premises at the same time? See new office IT setup. For the equipment room itself, see server room and rack setup.

Questions people ask

How often should a business replace its network equipment?

As a rule of thumb, firewalls and Wi-Fi access points every five to seven years, switches every seven to ten years and UPS batteries every three to five years. The deciding factor is the vendor's security support date, which can arrive before the equipment wears out.

When does Cisco Catalyst 2960-X support end?

Cisco stopped releasing software maintenance for the Catalyst 2960-X family on October 31, 2023, and the last date of support, including security fixes, is October 31, 2027. Offices still running these switches should plan their replacement now.

Should we choose cloud-managed or self-managed network equipment?

Cloud-managed platforms such as Meraki suit businesses with several sites or limited in-house IT, at the cost of an annual licence per device. Licence-free platforms such as UniFi cost less over time and suit offices with a provider who manages them actively.

Do we need Wi-Fi 7?

Not necessarily. Wi-Fi 6E is mature and well priced and uses the same 6 GHz band. Wi-Fi 7 makes sense if you keep access points for many years and are buying newer laptops. Either way, plan multi-gig switch ports and enough PoE power for the new access points.

Can a network refresh be done without downtime?

Close to it. With everything configured and labelled in advance, the cutover happens over a weekend, devices are tested before Monday, and the old equipment stays in place as a fallback. Most staff notice nothing except better Wi-Fi.

Should we replace the cabling during a network refresh?

Only if testing shows faults or the cabling is older than Category 5e. Good Category 6 cabling usually outlasts several generations of switches and access points. Test it during the audit so problems are fixed before new equipment goes in.

How long does a network refresh take?

For a typical office, about eight to ten weeks from audit to final documentation, with most of that time spent on design, ordering and pre-configuration. The actual cutover usually takes one weekend.

Can we refresh in stages to spread the cost?

Yes. The firewall is often replaced first if it is the oldest or least supported device. Switches and Wi-Fi are best done together, because new access points depend on switch port speed and power.